E&P Slaps Gold Fields With Twin Claims Nearing $740 Million Over Damang and Tarkwa Contracts

A major commercial dispute is unfolding in Ghana’s mining sector as Engineers & Planners Company Limited (E&P) launches two high-value claims against Gold Fields and its Ghanaian subsidiaries, with combined demands approaching $740 million.

The Ghanaian mining contractor is seeking $264.7 million related to operations at the Damang Mine and a further $474.9 million tied to Tarkwa’s Zone Two pits. Together, the claims represent one of the most significant contractor-owner confrontations in the country’s gold industry in recent years.

At the heart of E&P’s case is a broader accusation that Gold Fields imposed commercially unsustainable contract terms on a major local contractor while continuing to benefit from its operational output across multiple sites.

In a notice dated February 24, 2026, E&P accuses Abosso Gold Fields Limited of forcing it into an unfavorable contract structure dating back to 2016. According to the contractor, it was required to purchase a mining fleet from the mine owner for $7.1 million, only to later discover that the equipment was aged, obsolete, and unsuitable for operations. The company says it had to scrap the fleet and secure replacements through high-interest financing.

E&P also claims it accepted a mining rate of $3.2 per tonne based on assurances that the price would later be reviewed upward — a revision it says never materialized. The company insists its grievances are not due to poor performance, noting that by July 2019 it had mined 43 million tonnes, exceeding the scheduled target of 36 million tonnes set for December that year.

The dispute reportedly deepened after 2020 when E&P took on additional work following the exit of BCM Ghana from one of the pits due to litigation. E&P claims it was promised access to BCM’s equipment, but the fleet was never provided, forcing it to rent machinery at high daily rates. The contractor estimates these circumstances generated losses of nearly $88 million, of which only about $20 million was subsidized.

Further complaints relate to pricing differences, with E&P alleging it was offered $4.03 per tonne for work that BCM had allegedly been offered $4.79 per tonne, a gap the company describes as discriminatory. The company also attributes significant losses to a single-lane ramp design introduced at the Huni pit in 2021, which it says caused delays, increased fuel consumption, and reduced efficiency. These factors are estimated to have added about $72 million in losses, with minimal compensation provided.

Altogether, the Damang claim totals $264.7 million, covering equipment costs, third-party rentals, financing expenses, rate disparities, and operational delays.

In a separate notice dated March 9, 2026, E&P argues that it was systematically underpaid for contract mining work at the Akontansi and Kottraverchy pits in Tarkwa’s Zone Two. The company says it entered agreements beginning in 2018, followed by another in September 2021, but later challenged the rates being paid.

According to the notice, Gold Fields commissioned three independent reviews to determine appropriate minimum pricing, and those studies allegedly supported higher rates. However, E&P claims the revised pricing was never implemented, despite reported approval at the company’s board level in South Africa.

E&P further states that it was not allowed to negotiate freely and had to rely on loans — either from Gold Fields itself or external lenders — to finance equipment, supplies, and ongoing operations. Based on these factors, the contractor estimates its cumulative losses and unpaid earnings at approximately $474.9 million, arguing that the contract’s economics were flawed from the outset.

Both notices formally escalate the dispute beyond routine contractual disagreements. The Damang filing is described as a final notice under the contract, warning that E&P will proceed to arbitration if an amicable settlement is not reached. The Tarkwa notice similarly gives Gold Fields 14 days to enter good-faith negotiations before further legal action is pursued.

Significantly, the documents were copied to Ghana’s Minister of Lands and Natural Resources and the Chief Executive Officer of the Minerals Commission, signaling that E&P views the matter as one with regulatory and national importance rather than a purely private commercial quarrel.

The dispute comes at a sensitive time, as Gold Fields prepares to hand over the Damang Mine in April 2026. Beyond the transition, the confrontation could trigger wider debate about how risks, costs, and rewards are shared between multinational mining companies and local contractors in Ghana’s lucrative gold sector.

Gold Fields’ response to the allegations was not included in the documents reviewed, meaning the claims remain E&P’s assertions until addressed through negotiation, arbitration, or court proceedings.

Source: Norvanreport

0 0 votes
Article Rating
guest
Optional

0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Posts Tile

0
Would love your thoughts, please comment.x
()
x